October 15, 2026
When a motorboat passes the Southport pier, its wake rolls under the pilings and hits the stone riprap that protects the waterfront. Inside Climate News described that exact scene in January, then asked readers to imagine the same force multiplied a thousand or ten thousand times by the ships that use the river.
That multiplied force is why there are now trucks, rock and closed traffic lanes along Bay Street. The City of Southport's Shorefront Improvements Project started on-site construction October 1, 2026. It covers the Cape Fear River waterfront along West and East Bay Streets from South Caswell Avenue to South Atlantic Avenue. The project is designed around the river Southport has now. A separate decision about how big the ships in that river will get is still pending, and it is being made somewhere else.
Bay Street is closed to traffic from October 9 through October 30, 2026, and the city has posted a detour map with the notice. The text of the notice doesn't say where the closure starts and ends, so the map is the best guide before you drive down to the water. WECT also published the detour when the closure took effect.
The October closure is only the opening stretch. According to the city's project page, construction moves from west to east in three segments, with completion expected by March 31, 2027:
| Segment | Area | Anticipated dates |
|---|---|---|
| Segment 1 | Western area | October 1, 2026 to February 8, 2027 |
| Segment 2 | Central area | December 16, 2026 to March 1, 2027 |
| Segment 3 | Eastern area | February 12, 2027 to March 23, 2027 |
The segments overlap. From mid-December through early February, crews are scheduled to work the western and central areas at the same time. In mid-February the eastern segment starts while the central one is still underway. The city says the schedule can change with weather and field conditions. It also says residents should expect construction traffic, heavy equipment, temporary work zones, some noise, possible parking or traffic restrictions, and short-term limits on public access in parts of the project area.
The project area includes the town's most-used waterfront. Waterfront Park is on Bay Street between Howe and Davis Streets. The City Pier sits next to the park, and the Riverwalk starts near the pier and follows Bay Street west before it loops around the Yacht Basin, according to Brunswick County's tourism authority. The pilots' tower, a familiar West Bay Street landmark, is on the same stretch.
City Engineer Bob Jarvis listed the work for the Board of Aldermen in June: offshore breakwaters, beach nourishment, dune restoration, native plantings and rock revetments. The city's project page groups that work into three parts: shoreline protection, beach restoration and dune enhancement. It says the goal is to make the waterfront more resilient and to reduce shoreline erosion and storm damage.
In earlier planning discussions reported by the State Port Pilot, one riprap breakwater was planned in front of the pilots' tower, and the first phase was meant mainly to protect Bay Street and the Waterfront Park bulkhead. The city's current page describes the awarded work by corridor and segment, so treat those landmark-by-landmark details as earlier design talk, not a final site plan.
The June 11, 2026 board minutes explain why construction on a working waterfront isn't more disruptive. Jeremy Packard of Foth, the city's engineering consultant, told aldermen that most materials would be stored off-site. Only the parking lot beside Oliver's restaurant and the harbor walk along the park would serve as small staging areas, and the contractor would be allowed to bring in just one day's worth of material at a time.
The minutes also describe other safeguards:
The board voted unanimously to award the construction contract to Civil Works Contracting, LLC for $3,294,674.47. That was the lowest of four bids, which ranged from about $3.3 million to $4.3 million. Jarvis told the board the three lowest bids were within about four percent of each other and close to the engineer's estimate of $3.3 million. The bid also covered alternate segments, and staff recommended including them because the bids fit within the available budget.
The money comes from the state. A $5 million grant from the State Emergency Response and Disaster Relief Fund pays for the project, and Alderman Gross confirmed that no local match is required. State Rep. Charlie Miller and State Sen. Bill Rabon secured the grant in December 2021, and it carried a June 30, 2026 deadline. The contract award on June 11 came less than three weeks before that deadline. Surveys, engineering design, easement acquisition, permitting and public workshops took several years. Mayor Hatem noted that the effort began under former Mayor Robert Howard, with a committee chaired by Tommy Harrelson.
The State Port Pilot reported that Southport's Cape Fear River beach is eroding for three reasons: storm-driven waves, boat and ship traffic, and higher water levels. The same report said these pressures are expected to grow as the commercial ships using the Wilmington Harbor channel get bigger and come more often if the channel is deepened. In that article, Alderman Frank Lai put it plainly: "If we don't [do] this, with the wave action, the shoreline is going to be out here on Bay Street."
Wakes do damage across the river too. Battery Island is about half a mile from the Southport pier. It covers about 100 acres and is one of the largest wading-bird areas in the state. Inside Climate News reported that passing ferries and ships pull water away from the island's shore and then push it back hard. Thirty-year-old cedars there are falling into the river, and nests built above the usual high-tide line can still be flooded. "It's striking how far a boat wake can travel," a conservation advocate told the outlet. The state Wildlife Resources Commission told the Army Corps of Engineers that there was no information on wave heights or on how far wakes would travel onshore.
The U.S. Army Corps of Engineers published its final Letter Report and Environmental Impact Statement for the Wilmington Harbor 403 project on July 2, 2026. Coastal Review summarized the plan. It would extend the entrance of the federal channel by about 9 miles, deepen it from 42 feet to 47 feet, and widen parts of it along the roughly 28 miles from the river mouth to the Wilmington port. Construction is projected to start in 2030, take about six years and cost more than $1.3 billion. The North Carolina State Ports Authority says the deeper channel is needed for larger deep-draft container ships in East Coast to Asia trade.
North Carolina's Division of Coastal Management objected to the plan in February 2026, WECT reported. The objection sets off a formal federal dispute process, but it doesn't end the project. A division spokesperson told Coastal Review that the final EIS "acknowledges the State's federal consistency objection but does not resolve it." The last step in approval is a record of decision published in the Federal Register. None of the sources reviewed for this post shows that a record of decision had been issued as of October 12, 2026.
That puts two projects on two different timelines. The breakwaters, revetments and new sand along Bay Street are scheduled to be finished by the end of March 2027. If the deepening is approved, construction would start about three years after that. The State Port Pilot's reporting connects the two. It says the forces eroding Southport's riverfront beach are expected to get worse as a deeper channel brings larger ships, and brings them more often.
If the schedule holds, the eastern segment wraps up March 23, 2027, and the full project is complete by March 31. The finished waterfront will have restored beach, rebuilt dunes with native plants, rock protection along the bank and breakwaters offshore, all along the stretch where the park, the City Pier, the Riverwalk and the pilots' tower meet the river. After that, the contractor's one-year warranty applies, and the city plans to arrange separate post-construction monitoring.
The Bay Street waterfront is one of the things that make owning in Southport worthwhile, and our team follows how projects like this one shape the town's riverfront from season to season. If you have questions about what the Shorefront Improvements Project means for a property near the water or anywhere in the historic district, Better Beach Sales is glad to walk through it with you. Schedule a Consultation and Experience Oak Island.
Stay up to date on the latest real estate trends.
Imagine a place where work and play seamlessly blend into one fulfilling lifestyle. Our approach at Better Beach Sales goes beyond finding you the perfect home—it’s about building a community that thrives on collaboration and the natural beauty of Oak Island. Together, we can create opportunities, share success, and truly enjoy all that our coastal haven has to offer.